When the Quote Stops Being Right
Every estimate is built on what you could see. Then the job starts:
- Mold behind the refrigerator or under the sink cabinet.
- Carpet that looked fine, with a pad soaked through from pet urine or a slow leak.
- A move-out that's far dirtier than the listing photos, or a "light" post-construction clean with drywall dust in every vent.
- On restoration jobs, a wall opened for a small leak with a much bigger, older one behind it.
The work isn't the hard part. As one contractor put it in a discussion about a hidden bathroom leak that turned a routine job into thousands of dollars of water damage: that's where jobs go sideways, not in the work itself, but in the conversation after. The tool that keeps that conversation clean is the
change order: a short written agreement to change the scope and price of a job that's already underway.
Before the Job: Make Changes Expected, Not a Surprise
The owners who rarely fight over extra charges have usually settled it before the job started. Two things do most of the work:
- Say it in the estimate. An estimate is an estimate. A line like "This is an estimate based on the details provided. We confirm the final price on a walkthrough or when we arrive, and if anything is different from what was described, we'll tell you before any work starts" sets the expectation in one sentence.
- Put a change-order clause in your agreement. Say that conditions found on site that weren't visible or described (mold, water damage, biohazards, heavy buildup, extra rooms) are priced separately and need the customer's approval before the work is done. See how to write a cleaning service contract for where it fits.
As one commenter summed it up: write a good contract, reference change orders, and talk about it early, and it's much less of a burden later. If it's in the contract up front, nobody's surprised.
What to Do the Moment You Find It
- Stop the out-of-scope part, not the whole job. Keep doing what was agreed. Don't start on the new problem "since you're here anyway." Free extra work is how the "I never asked for that" argument starts.
- Document it. Take photos and a short video before you touch anything, with something in frame for scale. Note the time and the location in the home.
- Tell the customer right away. Call or talk in person while you're still on site, and follow up in writing within minutes.
- Give options with prices. For example: (a) handle it now for $X, (b) leave it and finish the original job, or (c) refer it to a specialist. Some things aren't a cleaning job at all. For mold, the EPA's guidance treats roughly 10 square feet as the point beyond which you should follow its professional remediation guidelines rather than a simple clean-up.
- Get written approval before doing the added work. One commenter's rule: get the change order paid before work goes forward. For small changes, written approval is usually enough. For big ones, take payment or a deposit first.
- Finish the original scope whether or not they approve the change, unless the new problem makes it unsafe.
On larger jobs, some contractors give the customer a short window (a few days) to accept the change in writing, and don't start the changed work until it's approved and paid.
Is a "Yes" by Text Enough?
A reply by text or email is a written record, and under the federal E-SIGN Act an electronic record or signature can't be refused legal effect just because it's electronic. The real weakness of a text "yes" is that it's usually vague. "Sure, go ahead" in reply to a photo doesn't say what was approved or for how much.
Make the message do the work. Send something the customer can't misread:
Example text: "Change order #1, 14 Oak St. Found mold behind the refrigerator, about 4 sq ft (photos attached). Treatment and cleaning of the area: $185, added to today's invoice. Reply YES to approve. We won't start on it until you do."
A "YES" to that names the work, the price and the job. For anything large, or with a customer who's already pushing back, use a signed change order or e-signature document instead. This isn't legal advice. For big restoration jobs, have a lawyer look at your change-order form once.
How to Keep Track of Changes
The customer should always know where the job stands. Keep it simple:
- Number every change (Change order #1, #2...) and keep them in one place per job: the job notes, your CRM, or a shared folder with the photos.
- Show changes separately on the invoice: the original job, then "Change order #1: mold treatment behind refrigerator (approved by text, 3/14), $185." A customer who sees their own approval on the invoice rarely disputes it.
- Send a short running total when there's more than one change: "Original $420 + Change #1 $185 = $605."
Price It Consistently, Not on the Spot
The worst time to invent a price is standing in someone's kitchen. Have your rates for the common surprises ready ahead of time: mold treatment by area, extra rooms, pet-damaged carpet, heavy buildup, haul-away. Then the number you quote mid-job matches what you'd have quoted if you'd known up front. For the bigger categories, see our guides to mold remediation costs and water damage restoration costs. And if your quotes keep missing because of what gets captured at the walkthrough, that's a process fix: see why cleaning quotes are still inconsistent.
FAQ
What is a change order in cleaning?
A short written agreement, made after a job has started, that changes its scope and price, such as adding mold treatment discovered on site. The customer approves it before the extra work is done.
Can I charge more than the quote if I find hidden damage?
Yes, for the additional work, if the customer approves it. The original quote covers the original scope. Explain what you found, show photos, give a price, and get written approval before starting.
Is a text message approval legally binding?
A text or email can be a valid written record, and federal law (the E-SIGN Act) doesn't let an agreement be refused just because it's electronic. Make the message specific (what, where, price) and keep it with the photos. For large amounts, use a signed change order.
Should I get paid before doing the change-order work?
For large changes, yes: take payment or a deposit first. For small add-ons on a job you're invoicing anyway, written approval plus a separate line on the invoice is usually enough.